Prepared for
Shark Bay Resources Pty Ltd
Useless Loop · Heirisson Prong · Shark Bay, Western Australia
Project
Bitterns Recycling — Field Piping Installation
PROJECT-SPECIFIC

Environment, Health &
Safety Management Plan

Document numberDTL-PRJ0072-HSE-001
RevisionA — Issued for Approval
Date16 July 2026
AttentionMr John Stephens — Principal Representative
Contract · Purchase orderSBS10627 · PO 182113
Scope of work23092-SOW-024rD, Section 7
Reads withSBR-PRO-0082 (SBR Contractor Management Procedure) & SBR EH&S Management Plan
Submitted underSOW 7.1 — project-specific EH&S Plan, for SBR review & approval prior to mobilisation
DTL (WA) Pty Ltd  ·  2/28 Horus Bend, Bibra Lake WA 6163  ·  ABN 45 677 646 454  ·  Commercial-in-Confidence
DTL (WA) Pty Ltd · Commercial-in-ConfidenceContract SBS10627 · PO 182113Page 1 of 18
EH&S Management PlanBitterns Recycling Project — Field Piping Installation
DTL-PRJ0072-HSE-001
Rev A

§Document control

Revision history

RevDateDescription of changeByChkApp
A16 Jul 2026Issued to SBR for review & approvalSHTK 
      
HOLD — two items to close this Plan. (1) SBR to provide SBR-PRO-0082, the Contractor Management Procedure that sets the minimum EH&S requirements this Plan must meet (SOW 7.1); this Plan will be updated to confirm alignment on receipt. (2) SBR to confirm which of its site permits apply (SOW 7.1) so the permit schedule in Section 9 can be finalised.

Approval

PREPARED — DTL
Sean Heron
Project Manager · Date
AUTHORISED — DTL
Tyson Knight
Director & Contractor Representative · Date
REVIEWED — SBR
Principal Representative · Date
APPROVED — SBR
for mobilisation · Date
DTL (WA) Pty Ltd · Commercial-in-ConfidenceContract SBS10627 · PO 182113Page 2 of 18
EH&S Management PlanBitterns Recycling Project — Field Piping Installation
DTL-PRJ0072-HSE-001
Rev A

§Contents

1Purpose & alignment with SBR2Scope & battery limits3Roles, responsibilities & supervision4Pre-mobilisation personnel requirements5Inductions & site access6Fitness for work — drug & alcohol7Risk management & the CRAW8Hydrocarbon, contamination & waste control9Permits, traffic & interface management10Emergency & environmental management11Consultation, communication & reporting12Monitoring, audit & review13Supporting DTL system documents
DTL (WA) Pty Ltd · Commercial-in-ConfidenceContract SBS10627 · PO 182113Page 3 of 18
EH&S Management PlanBitterns Recycling Project — Field Piping Installation
DTL-PRJ0072-HSE-001
Rev A

1Purpose & alignment with SBR

This project-specific Environment, Health & Safety (EH&S) Management Plan sets out how DTL (WA) Pty Ltd will manage EH&S for the Bitterns Recycling Field Piping Installation at the Useless Loop operation. It is submitted under SOW 7.1 for SBR review and approval prior to site mobilisation, and supplements DTL’s corporate Health, Safety & Environment Management Plan (DTL-HSE-PLN-0001).

This Plan is read together with SBR-PRO-0082 (SBR Contractor Management Procedure) and SBR’s EH&S Management Plan. Where a requirement differs, the more stringent requirement applies, and SBR’s site rules govern on site.

1.1 Project-specific EH&S requirements (SOW 7.1)

In addition to SBR-PRO-0082, DTL will deliver each of the following, addressed in this Plan at the section shown:

SOW 7.1 requirementAddressed in
Preparation & submission of necessary SBR permitsSection 9
Construction Risk Assessment Workshop (CRAW)Section 7
Traffic management, barricading, signs & noticesSection 9
Interfaces with SBR maintenance, operations & other contractorsSection 9
Site works risk assessments (SWMS, JSA, Take 5)Section 7

1.2 EH&S objective

DTL is committed to a zero-harm outcome: no injury to people, no damage to SBR infrastructure, and no contamination of the sensitive crystalliser-pond environment. Higher-order controls (eliminate, substitute, isolate, engineer) are preferred over administrative controls and PPE.

DTL (WA) Pty Ltd · Commercial-in-ConfidenceContract SBS10627 · PO 182113Page 4 of 18
EH&S Management PlanBitterns Recycling Project — Field Piping Installation
DTL-PRJ0072-HSE-001
Rev A

2Scope & battery limits

This Plan applies to all DTL personnel, subcontractors, plant and visitors engaged on the Works — the supply and installation of the Bitterns recycling and seawater flush field piping, including HDPE butt-fusion, road crossings, tie-ins, standpipes and associated civil works.

It applies from mobilisation to demobilisation, on all areas of the SBR site to which DTL is granted access, and to all interfacing activities described in Section 9.

Isolation, instrumentation and control works are performed by SBR electricians (SOW 7.7) and are outside DTL’s scope; DTL manages the interface, not the electrical works.

3Roles, responsibilities & supervision

Contractor RepresentativeTyson Knight (Director) — overall accountability; attends the weekly SBR status meeting (Contract cl. 9.4).
Site SupervisorNominated competent person responsible for general control of the Works and for the safety of the works and all personnel on site (SOW 7.3).
All personnelWork to this Plan, SWMS/JSAs and permits; stop work if unsafe; report all incidents, spills and near-misses immediately.
SBR Site RepresentativeProvides site oversight, permits and site-specific requirements; receives daily pre-starts and incident/spill notifications.
Statutory competency (SOW 7.3). The nominated site supervisor must be at least Schedule 26 (or Section 44) approved under the WHS Regulations. DTL will confirm the nominated supervisor and hold their evidence of approval in the personnel matrix (Section 4) before mobilisation.
DTL (WA) Pty Ltd · Commercial-in-ConfidenceContract SBS10627 · PO 182113Page 5 of 18
EH&S Management PlanBitterns Recycling Project — Field Piping Installation
DTL-PRJ0072-HSE-001
Rev A

4Pre-mobilisation personnel requirements (SOW 7.5)

Before any person mobilises to site, DTL will hold current evidence of each of the following for that person. No person mobilises without a complete record; the personnel matrix is maintained by DTL and made available to SBR on request.

RequirementCurrencyNotes
Pre-employment medicalwithin 12 months of mobilisationFit-for-work medical.
Drug & alcohol screenwithin 30 days of first mobilisationTimed to the mobilisation date — not run early.
Police clearancewithin 12 months of mobilisationLong lead — commenced immediately.
Tickets / qualifications matrixcurrentCopies of all tickets & competencies; all high-risk work licences; and current VOCs from nationally accredited RTOs.
Tracked in DTL’s Training & Competency Register (DTL-HSE-REG-0004) and Licence & Ticket (HRWL) Register (DTL-HSE-REG-0007).

5Inductions & site access (SOW 7.2)

DTL (WA) Pty Ltd · Commercial-in-ConfidenceContract SBS10627 · PO 182113Page 6 of 18
EH&S Management PlanBitterns Recycling Project — Field Piping Installation
DTL-PRJ0072-HSE-001
Rev A

6Fitness for work — drug & alcohol (SOW 7.4)

SBR requires 0.00% BAC on the operational site. All personnel are subject to a drug & alcohol screen on arrival, plus daily alcohol testing while on site. Random or for-cause D&A screens may occur at any time. Refusal to comply results in immediate removal from site.

DTL applies its Fatigue Management (DTL-HSE-POL-0003) and Fitness for Work (DTL-HSE-POL-0007) policies, and adopts the SBR 0.00% standard as the governing requirement on site. Work hours are managed to control fatigue; supervisors monitor for signs of impairment and fatigue and stand personnel down where necessary.

7Risk management & the CRAW (SOW 7.6)

All site works and tasks are risk-assessed using JSA/JHA, Safe Work Instructions and Take 5s, following DTL’s Risk Management Procedure (DTL-HSE-PRO-0003) and the risk matrix and hierarchy of control in the corporate Plan. Controls are identified and implemented to eliminate or mitigate each hazard; task risk assessments are signed by the crew and held on the job file.

7.1 Construction Risk Assessment Workshop (CRAW)

Client approval loop — long lead. A CRAW will be carried out pre-mobilisation to identify, at a high level, all hazards and risks of the Works and the controls that remove or mitigate them. SBR will be invited to attend, and the final risk assessment (specifically the controls) must be reviewed and approved by SBR before DTL mobilises (SOW 7.6). The CRAW output populates the project Risk Register (DTL-HSE-REG-0006). Booking the CRAW is the critical path to mobilisation.
DTL (WA) Pty Ltd · Commercial-in-ConfidenceContract SBS10627 · PO 182113Page 7 of 18
EH&S Management PlanBitterns Recycling Project — Field Piping Installation
DTL-PRJ0072-HSE-001
Rev A

8Hydrocarbon, contamination & waste control (SOW 7.8)

Because of the sensitive environment and the proximity to the SBR crystalliser ponds, strict controls prevent and contain hydrocarbon spills and other contamination. DTL’s hydrocarbon and contamination control procedures are provided to SBR for approval prior to mobilisation and describe managing, storage, handling, controls, prevention and clean-up.

8.1 Waste & wind-blown contamination

DTL (WA) Pty Ltd · Commercial-in-ConfidenceContract SBS10627 · PO 182113Page 8 of 18
EH&S Management PlanBitterns Recycling Project — Field Piping Installation
DTL-PRJ0072-HSE-001
Rev A

9Permits, traffic & interface management (SOW 7.1, 7.7)

9.1 Permits

DTL prepares and submits the necessary SBR permits before the relevant work begins, and applies its own permit-to-work system (DTL-HSE-PRO-0024) for high-risk activities — excavation / ground disturbance, hot works, working at heights, confined space, crane & lifting, and electrical / energised services.

Confirm with SBR: the schedule of SBR permits that apply to this scope, so the permit register can be finalised.

9.2 Traffic management

A project Traffic Management Plan (DTL-HSE-PRO-0016) provides temporary barricading, safety signs and notices for the work areas, segregation of plant and personnel, spotters and UHF comms, and compliance with site speed limits and exclusion zones.

9.3 Interface areas (SOW 7.7)

DTL understands and manages the following interfaces, with planned traffic movements past the pipeline installation area:

DTL (WA) Pty Ltd · Commercial-in-ConfidenceContract SBS10627 · PO 182113Page 9 of 18
EH&S Management PlanBitterns Recycling Project — Field Piping Installation
DTL-PRJ0072-HSE-001
Rev A

10Emergency & environmental management

Site emergency arrangements, assembly points and wardens are established before work starts; first aid and emergency equipment are provided and maintained; drills are conducted and reviewed. DTL follows its Emergency Response Plan (DTL-HSE-PRO-0006) and Emergency Management Procedure (DTL-HSE-PRO-0020), aligned to SBR’s site emergency arrangements.

11Consultation, communication & reporting (SOW 7.9)

DTL (WA) Pty Ltd · Commercial-in-ConfidenceContract SBS10627 · PO 182113Page 10 of 18
EH&S Management PlanBitterns Recycling Project — Field Piping Installation
DTL-PRJ0072-HSE-001
Rev A

12Monitoring, audit & review

13Supporting DTL system documents

This Plan draws on DTL’s controlled EH&S management system. Key supporting documents:

Doc No.Document
DTL-HSE-PLN-0001Health, Safety & Environment Management Plan (corporate)
DTL-HSE-PRO-0003Risk Management Procedure
DTL-HSE-PRO-0006 / 0020Emergency Response Plan / Emergency Management Procedure
DTL-HSE-PRO-0016Traffic Management Plan
DTL-HSE-PRO-0018Hazardous Chemicals Procedure
DTL-HSE-PRO-0023Waste Management Procedure
DTL-HSE-PRO-0024Permit to Work Procedure
DTL-HSE-POL-0002 / 0003 / 0007Drug & Alcohol / Fatigue / Fitness for Work policies
DTL-HSE-REG-0004 / 0006 / 0007Training & Competency / Risk / Licence & Ticket registers
Full controlled-document status is maintained in DTL’s document register (2iB).
DTL (WA) Pty Ltd · Commercial-in-ConfidenceContract SBS10627 · PO 182113Page 11 of 18