Prepared for
Shark Bay Resources Pty Ltd
Useless Loop · Heirisson Prong · Shark Bay, Western Australia
Project
Bitterns Recycling — Field Piping Installation
PROJECT-SPECIFIC
Environment, Health &
Safety Management Plan
| Document number | DTL-PRJ0072-HSE-001 |
| Revision | A — Issued for Approval |
| Date | 16 July 2026 |
| Attention | Mr John Stephens — Principal Representative |
| Contract · Purchase order | SBS10627 · PO 182113 |
| Scope of work | 23092-SOW-024rD, Section 7 |
| Reads with | SBR-PRO-0082 (SBR Contractor Management Procedure) & SBR EH&S Management Plan |
| Submitted under | SOW 7.1 — project-specific EH&S Plan, for SBR review & approval prior to mobilisation |
DTL (WA) Pty Ltd · 2/28 Horus Bend, Bibra Lake WA 6163
· ABN 45 677 646 454 · Commercial-in-Confidence
DTL (WA) Pty Ltd · Commercial-in-ConfidenceContract SBS10627 · PO 182113Page 1 of 18
EH&S Management PlanBitterns Recycling Project — Field Piping Installation
DTL-PRJ0072-HSE-001
Rev A
§Document control
Revision history
| Rev | Date | Description of change | By | Chk | App |
| A | 16 Jul 2026 | Issued to SBR for review & approval | SH | TK | |
| | | | | | |
HOLD — two items to close this Plan. (1) SBR to provide SBR-PRO-0082,
the Contractor Management Procedure that sets the minimum EH&S requirements this Plan must meet (SOW 7.1);
this Plan will be updated to confirm alignment on receipt. (2) SBR to confirm which of its site permits apply
(SOW 7.1) so the permit schedule in Section 9 can be finalised.
Approval
PREPARED — DTL
Sean Heron
Project Manager · Date
AUTHORISED — DTL
Tyson Knight
Director & Contractor Representative · Date
REVIEWED — SBR
Principal Representative · Date
APPROVED — SBR
for mobilisation · Date
DTL (WA) Pty Ltd · Commercial-in-ConfidenceContract SBS10627 · PO 182113Page 2 of 18
EH&S Management PlanBitterns Recycling Project — Field Piping Installation
DTL-PRJ0072-HSE-001
Rev A
§Contents
DTL (WA) Pty Ltd · Commercial-in-ConfidenceContract SBS10627 · PO 182113Page 3 of 18
EH&S Management PlanBitterns Recycling Project — Field Piping Installation
DTL-PRJ0072-HSE-001
Rev A
1Purpose & alignment with SBR
This project-specific Environment, Health & Safety (EH&S) Management Plan sets out how
DTL (WA) Pty Ltd will manage EH&S for the Bitterns Recycling Field Piping Installation at
the Useless Loop operation. It is submitted under SOW 7.1 for SBR review and approval prior to
site mobilisation, and supplements DTL’s corporate Health, Safety & Environment Management Plan
(DTL-HSE-PLN-0001).
This Plan is read together with SBR-PRO-0082 (SBR Contractor Management Procedure)
and SBR’s EH&S Management Plan. Where a requirement differs, the more stringent requirement
applies, and SBR’s site rules govern on site.
1.1 Project-specific EH&S requirements (SOW 7.1)
In addition to SBR-PRO-0082, DTL will deliver each of the following, addressed in this Plan at the
section shown:
| SOW 7.1 requirement | Addressed in |
| Preparation & submission of necessary SBR permits | Section 9 |
| Construction Risk Assessment Workshop (CRAW) | Section 7 |
| Traffic management, barricading, signs & notices | Section 9 |
| Interfaces with SBR maintenance, operations & other contractors | Section 9 |
| Site works risk assessments (SWMS, JSA, Take 5) | Section 7 |
1.2 EH&S objective
DTL is committed to a zero-harm outcome: no injury to people, no damage to SBR infrastructure,
and no contamination of the sensitive crystalliser-pond environment. Higher-order controls (eliminate,
substitute, isolate, engineer) are preferred over administrative controls and PPE.
DTL (WA) Pty Ltd · Commercial-in-ConfidenceContract SBS10627 · PO 182113Page 4 of 18
EH&S Management PlanBitterns Recycling Project — Field Piping Installation
DTL-PRJ0072-HSE-001
Rev A
2Scope & battery limits
This Plan applies to all DTL personnel, subcontractors, plant and visitors engaged on the Works —
the supply and installation of the Bitterns recycling and seawater flush field piping, including HDPE
butt-fusion, road crossings, tie-ins, standpipes and associated civil works.
It applies from mobilisation to demobilisation, on all areas of the SBR site to which DTL is granted
access, and to all interfacing activities described in Section 9.
Isolation, instrumentation and control works are performed by SBR electricians
(SOW 7.7) and are outside DTL’s scope; DTL manages the interface, not the electrical works.
3Roles, responsibilities & supervision
| Contractor Representative | Tyson Knight (Director) — overall accountability; attends the weekly SBR status meeting (Contract cl. 9.4). |
| Site Supervisor | Nominated competent person responsible for general control of the Works and for the safety of the works and all personnel on site (SOW 7.3). |
| All personnel | Work to this Plan, SWMS/JSAs and permits; stop work if unsafe; report all incidents, spills and near-misses immediately. |
| SBR Site Representative | Provides site oversight, permits and site-specific requirements; receives daily pre-starts and incident/spill notifications. |
Statutory competency (SOW 7.3). The nominated site supervisor must be at least
Schedule 26 (or Section 44) approved under the WHS Regulations. DTL will confirm the nominated
supervisor and hold their evidence of approval in the personnel matrix (Section 4) before mobilisation.
DTL (WA) Pty Ltd · Commercial-in-ConfidenceContract SBS10627 · PO 182113Page 5 of 18
EH&S Management PlanBitterns Recycling Project — Field Piping Installation
DTL-PRJ0072-HSE-001
Rev A
4Pre-mobilisation personnel requirements (SOW 7.5)
Before any person mobilises to site, DTL will hold current evidence of each of the following for that
person. No person mobilises without a complete record; the personnel matrix is maintained by DTL and
made available to SBR on request.
| Requirement | Currency | Notes |
| Pre-employment medical | within 12 months of mobilisation | Fit-for-work medical. |
| Drug & alcohol screen | within 30 days of first mobilisation | Timed to the mobilisation date — not run early. |
| Police clearance | within 12 months of mobilisation | Long lead — commenced immediately. |
| Tickets / qualifications matrix | current | Copies of all tickets & competencies; all high-risk work licences; and current VOCs from nationally accredited RTOs. |
Tracked in DTL’s Training & Competency Register (DTL-HSE-REG-0004) and
Licence & Ticket (HRWL) Register (DTL-HSE-REG-0007).
5Inductions & site access (SOW 7.2)
- All DTL and subcontractor personnel complete the SBR induction (computer-based, ~2.5 hrs,
completed off site) before mobilising and commencing work.
- Anyone driving a light vehicle on site completes the light-vehicle VOC (allow ~1 hr per person).
- Delivery drivers may be escorted to the worksite without induction but remain subject to Fitness for Work (Section 6).
- Site access and attendance are recorded (DTL-HSE-REG-0002 Site Access Register; DTL-HSE-FRM-0007 Sign-On).
DTL (WA) Pty Ltd · Commercial-in-ConfidenceContract SBS10627 · PO 182113Page 6 of 18
EH&S Management PlanBitterns Recycling Project — Field Piping Installation
DTL-PRJ0072-HSE-001
Rev A
6Fitness for work — drug & alcohol (SOW 7.4)
SBR requires 0.00% BAC on the operational site. All personnel are subject to a
drug & alcohol screen on arrival, plus daily alcohol testing while on site. Random or
for-cause D&A screens may occur at any time. Refusal to comply results in immediate removal from site.
DTL applies its Fatigue Management (DTL-HSE-POL-0003) and Fitness for Work (DTL-HSE-POL-0007) policies,
and adopts the SBR 0.00% standard as the governing requirement on site. Work hours are managed to control
fatigue; supervisors monitor for signs of impairment and fatigue and stand personnel down where necessary.
7Risk management & the CRAW (SOW 7.6)
All site works and tasks are risk-assessed using JSA/JHA, Safe Work Instructions and Take 5s, following
DTL’s Risk Management Procedure (DTL-HSE-PRO-0003) and the risk matrix and hierarchy of control in the
corporate Plan. Controls are identified and implemented to eliminate or mitigate each hazard; task risk
assessments are signed by the crew and held on the job file.
7.1 Construction Risk Assessment Workshop (CRAW)
Client approval loop — long lead. A CRAW will be carried out
pre-mobilisation to identify, at a high level, all hazards and risks of the Works and the controls
that remove or mitigate them. SBR will be invited to attend, and the final risk assessment
(specifically the controls) must be reviewed and approved by SBR before DTL mobilises (SOW 7.6).
The CRAW output populates the project Risk Register (DTL-HSE-REG-0006). Booking the CRAW is the critical
path to mobilisation.
DTL (WA) Pty Ltd · Commercial-in-ConfidenceContract SBS10627 · PO 182113Page 7 of 18
EH&S Management PlanBitterns Recycling Project — Field Piping Installation
DTL-PRJ0072-HSE-001
Rev A
8Hydrocarbon, contamination & waste control (SOW 7.8)
Because of the sensitive environment and the proximity to the SBR crystalliser ponds, strict
controls prevent and contain hydrocarbon spills and other contamination. DTL’s hydrocarbon and
contamination control procedures are provided to SBR for approval prior to mobilisation and describe
managing, storage, handling, controls, prevention and clean-up.
- Spill kits maintained on site; refuelling in designated bunded areas only.
- Plant checked daily for leaks; drip trays under static plant.
- All spills and contamination, no matter how small, reported to the SBR site representative immediately.
- Chemicals registered with SDS (DTL-HSE-REG-0001); handling per DTL-HSE-PRO-0018.
8.1 Waste & wind-blown contamination
- Rubbish and waste managed so there is no risk of wind-blown contamination of the crystalliser ponds;
DTL provides its own bins where necessary (DTL-HSE-PRO-0023 Waste Management).
- No glass is taken into the ponds area (per the SBR induction).
DTL (WA) Pty Ltd · Commercial-in-ConfidenceContract SBS10627 · PO 182113Page 8 of 18
EH&S Management PlanBitterns Recycling Project — Field Piping Installation
DTL-PRJ0072-HSE-001
Rev A
9Permits, traffic & interface management (SOW 7.1, 7.7)
9.1 Permits
DTL prepares and submits the necessary SBR permits before the relevant work begins, and applies
its own permit-to-work system (DTL-HSE-PRO-0024) for high-risk activities — excavation / ground
disturbance, hot works, working at heights, confined space, crane & lifting, and electrical / energised
services.
Confirm with SBR: the schedule of SBR permits that apply to this scope, so the
permit register can be finalised.
9.2 Traffic management
A project Traffic Management Plan (DTL-HSE-PRO-0016) provides temporary barricading, safety signs
and notices for the work areas, segregation of plant and personnel, spotters and UHF comms, and compliance
with site speed limits and exclusion zones.
9.3 Interface areas (SOW 7.7)
DTL understands and manages the following interfaces, with planned traffic movements past the pipeline
installation area:
- SBR electricians — isolation, instrumentation and control works.
- Project civil construction works.
- SBR and other contractors accessing the flume / pond areas via shared access and haul roads
adjacent to the construction site.
DTL (WA) Pty Ltd · Commercial-in-ConfidenceContract SBS10627 · PO 182113Page 9 of 18
EH&S Management PlanBitterns Recycling Project — Field Piping Installation
DTL-PRJ0072-HSE-001
Rev A
10Emergency & environmental management
Site emergency arrangements, assembly points and wardens are established before work starts; first aid
and emergency equipment are provided and maintained; drills are conducted and reviewed. DTL follows its
Emergency Response Plan (DTL-HSE-PRO-0006) and Emergency Management Procedure (DTL-HSE-PRO-0020), aligned
to SBR’s site emergency arrangements.
- Emergency contacts and nearest medical facility confirmed at induction and displayed on site.
- Environmental controls: spill response, dust suppression as required, and protection of client
infrastructure (e.g. pond liners).
- Waste segregated and disposed of lawfully; records kept in 2iB.
11Consultation, communication & reporting (SOW 7.9)
- Kick-off meeting with SBR before works commence.
- Daily pre-starts documented and forwarded to the SBR representative (DTL-HSE-FRM-0006).
- Daily site meetings and discussions with SBR as required.
- Weekly progress meetings with SBR stakeholders once site works commence — actual vs planned
progress, next-week plan, HSE concerns and any other issues.
- Toolbox talks and worker consultation recorded (DTL-HSE-FRM-0004, FRM-0008); H&S consultation per
DTL-HSE-PRO-0009.
DTL (WA) Pty Ltd · Commercial-in-ConfidenceContract SBS10627 · PO 182113Page 10 of 18
EH&S Management PlanBitterns Recycling Project — Field Piping Installation
DTL-PRJ0072-HSE-001
Rev A
12Monitoring, audit & review
- Site safety inspections and plant pre-starts conducted and recorded (DTL-HSE-CHK-0001, CHK-0002).
- Incidents and near-misses reported and investigated (DTL-HSE-PRO-0005; FRM-0001, FRM-0002); corrective
actions tracked to closure (DTL-HSE-REG-0009).
- HSE objectives and targets set and reviewed; this Plan reviewed at planned intervals and on change
(DTL-HSE-PRO-0017 Quarterly Self-Evaluation).
13Supporting DTL system documents
This Plan draws on DTL’s controlled EH&S management system. Key supporting documents:
| Doc No. | Document |
| DTL-HSE-PLN-0001 | Health, Safety & Environment Management Plan (corporate) |
| DTL-HSE-PRO-0003 | Risk Management Procedure |
| DTL-HSE-PRO-0006 / 0020 | Emergency Response Plan / Emergency Management Procedure |
| DTL-HSE-PRO-0016 | Traffic Management Plan |
| DTL-HSE-PRO-0018 | Hazardous Chemicals Procedure |
| DTL-HSE-PRO-0023 | Waste Management Procedure |
| DTL-HSE-PRO-0024 | Permit to Work Procedure |
| DTL-HSE-POL-0002 / 0003 / 0007 | Drug & Alcohol / Fatigue / Fitness for Work policies |
| DTL-HSE-REG-0004 / 0006 / 0007 | Training & Competency / Risk / Licence & Ticket registers |
Full controlled-document status is maintained in DTL’s document register (2iB).
DTL (WA) Pty Ltd · Commercial-in-ConfidenceContract SBS10627 · PO 182113Page 11 of 18